5-Story Residential Building – Construction Project Management

Role: Building Engineering & AEC Design

I managed the full-cycle documentation and planning for a 5-story residential building. Prepared a detailed Bill of Quantities (BOQ) with a total estimated bud

Engineering Tools: Microsoft Project, Microsoft Excel, AutoCAD & Revit, Microsoft Word

  • Project Value: Estimated at ~71.4 Million BDT (Approx. $600k USD).
  • Timeline: 18-month execution plan.
  • Procurement Method: Open Tendering Method (OTM) following public procurement standards.
  • Work Breakdown Structure (WBS): Decomposed the project into manageable phases (Foundation, Structure, MEP, Finishing) to track progress effectively.
  • 1. Project Schedule (Gantt Chart) A visual timeline from Microsoft Project showing the critical path and activity sequencing. [Placeholder for MSP Schedule Image]
  • 2. Bill of Quantities (BOQ) A detailed cost breakdown sheet from Excel showing material quantities and unit rates. [Display 3.2 BOQ.pdf (implied visual)]
  • 3. Tender Document Cover The official cover page of the tender package prepared for the "Dream House" project. [Display TENDER DOCUMENT 2012011docx_justified.docx (implied visual)]